GOLEN GOL HYDRO POWER PROJECT

 

  1. Salient Features of the Project:
1. Location District Chitral KP
2. Project Type  Run of the River
3. Installed capacity  108 MW ( 3 units – 36 MW each)
4. Weir Height  12 m
5. Length of Weir 40 m
6. Design Discharge  30 m3 / sec
7. Tunnel Length 3.8 km
8. Annual Energy  436 GWh
9. 1st Revised PC-I Cost Rs. 29.077 Billion
  1. Detail of Expenditure:

Total expenditure incurred upto 31st March, 2018 is Rs. 25,461.518 Million

  1. Detail of Loan:
S.No Donor Agency Loan No Total Loan Utilization Upto 31st March, 2018 Balance
1 `Saudi Fund for Development 10/479 40.000 39.525 0.475
2 `Saudi Fund for Development 14/609 57.800 46.424 11.376
3 Kuwait Fund for Development 742 52.500 37.000 15.500
4 OPEC Fund 1205P & 1206PB 30.000 22.594 7.406

 

  1. Updated Physical progress (Upto 31.03.2018) 
Description Progress Upto 31.03.2018 Remarks
Lot-1 (O&M staff Colony) 100% Substantially Completed
Lot-2 (Civil Works) 100% Substantially Completed. Defect Liability Period (DLP) started with effect from 27.08.2017.
Lot-3.1 (Civil Works for Powerhouse, Tailrace & Switchyard) 100% Substantially Completed. Defect Liability Period (DLP) started with effect from 19.12.2017.
Lot-3.2 (E&M Works) 95.28% Unit-1 commissioned on 23.01.2018 and started the commercial operation.

 

Dry testing of Unit-2 & 3 completed on 20.04.2018.

Wet commissioning of Unit-2 &3 with Transmission line will be carried out in July and August respectively.

Lot-4.1 (Transmission Line from Golen Gol to Chukiatan & Grid Station) 95.32% Completion Date is July-2018. Detail of progress achieved till to date is  attached
Lot-4.2 (Transmission Line Chukiatan to Chakdara) 74.44% Completion Date is August-2018. Detail of progress achieved till to date is  attached