Power House Progress Photos (PDF)
Intake Pictorial Progress (PDF)
Tarbela 4th Extension Hydropower Project
Salient Features of Project
Capacity | 1410 MW |
Generating Units | 3 x 470 MW |
Annual Energy Generation | 3840 GWh |
EIRR | 30.3% ~ 36. 7%: |
Cost per kWh as per PC-1 | Rs. 1.623 |
Date of Commencement | 29.10.2013 |
Date of Commissioning | 25.02.2018 |
Implementation Period | 5 Years |
History of Approval oF Project
- PC-I approved by ECNEC : 08.2012
- PC-I cost : PKR 83.6 billion with FEC 65.8 billion
Loan Detail
Donor | Loan No. | Loan Amount | Mark Up as per GOP Re-lending | Admn. Expenses /Commit-ment Fee | Sign. / Effective Date | Loan Closing Date | Grace Period (Years) | Re-payment Period (Years) |
IBRD | 8144 PK | US$ 400 million | 15% p.a | 0.25% | 27.4.2012 | 27.4.2019 | 07 | 18.5 |
IDA | 5079 PK | *US$ 440 million | 15% p.a | 0.5% (Commit. Fee) / 0.75% p.a (Service Charges) | 27.4.2012 | 27.4.2017 | 05 | 20 |
*US$ 115 million withdrawn from T4thHP and reallocated to other project by GoP during March 2016
Detail of Expenditure Incurred
- Total Project Cost (including IDC) as per = 928 Million USD
- Total Disbursement against Expenditure = 770.02 Million USD against 795.59 Million USD
- 98 % vs 85.73%
Updated Physical Progress
- 10% vs 95.85%